FEBETRA, Brussels, has informed us of the second phase of road works on the:
E411 (Brussels-Luxemburg) and E25 (Liège-Bastogne) motorways from 14.3.05 to 1.9.05 in four separate zones :
zone 1 : E25 (A26) between Ferrières and Houffalize (km 35.6 to 52.4)
zone 2 : E25 (A26) between Houffalize and Bastogne (km 52.4 to 80.6)
zone 3 : E411 (A4) between Libramont and Tellin (km 130 to 109.4)
zone 4 : E411 (A4) between Neufchâteau and Habay (km 145.6 to 158.1)
alternative routes :
Liège-Verviers-Sankt Vith (B) — Prüm-Trier (D) — Luxemburg (L)
Brussels-Mons (B) — Valenciennes-Cambrai-Reims-Langres-Dijon (F) (this route is particularly recommended from 24.4.05 for vehicles heading towards Belgium owing to major road works on the A31 at the Richemont viaduct north of Metz)
Antwerp ringroad in the direction of Ghent and the intersections with the E313/E34, E19 and A12 motorways
from 26.3.05 to 15.9.05, vehicles in transit and those heading for the port of Antwerp will be obliged to use the Antwerp ringroad on which, three weeks later, traffic will be reduced to 2x2 lanes; in July, the Kennedy tunnel will be closed to vehicles of over 2m wide.
Source International Road Transport Union